CBA advises Hera in litigation concerning cogeneration incentives: Council of State upholds appeal

CBA advised Hera S.p.A. in proceedings before the Italian Council of State, which resulted in the annulment of the decisions whereby the Energy Services Manager (Gestore dei Servizi Energetici – GSE) had denied the company access to incentives available for high-efficiency cogeneration.

The dispute concerned a cogeneration plant in Forlì, which became operational in 2016 and was recognised by the GSE as a high-efficiency cogeneration unit. The GSE had nevertheless rejected Hera’s application for the allocation of Energy Efficiency Certificates (TEE), on the grounds that the plant did not meet the requirements set out in Ministerial Decree of 5 September 2011 to qualify as a “new cogeneration unit”. According to the GSE, one of the components used in the plant was not new, namely an internal combustion engine previously operated at another facility and subsequently overhauled.

In judgment No. 8024/2025, the Council of State upheld Hera’s appeal, overturning the judgment of the Lazio Regional Administrative Court (TAR Lazio) No. 14501/2025 and annulling the GSE’s decisions insofar as they denied the company the benefits claimed for the 2017 production year.

The judgment clarified that, for the purposes of accessing the support scheme, the applicable legislation requires the construction of a new cogeneration unit brought into operation after 7 March 2007, but does not require the individual components of the plant to be new or previously unused. According to the Council of State, the concept of “new construction” refers to the creation of a standalone production unit that did not previously exist, rather than to the absolute novelty of each component used.

The Court also held that the GSE’s interpretation would have introduced an additional and particularly restrictive requirement for access to the support scheme, with no basis in either primary or secondary legislation.

Hera S.p.A. was assisted by CBA Studio Legale e Tributario with a team led by partner Francesco Piron, comprising of counsel Tiziana Sogari and associate Massimino Crisci.

Related articles
08-04-2026

Press releases

CBA advises BCC Banca Iccrea and BCC Veneta on ship financing for Zeta S.r.l.
Read more
01-04-2026

Press reviews

The repair clause under the new industrial design framework
Read more
01-04-2026

Press reviews

Integrated workplace health and safety plan 2026: a broad-based approach to safety
Read more
01-04-2026

Press releases

CBA strengthens its Compliance, Data Protection & Cybersecurity practice with the addition of Riccardo Guarino
Read more
20-03-2026

Press reviews

Omnibus I: how corporate sustainability rules are changing
Read more
20-03-2026

Press reviews

VAT on electricity system charges: the Bologna Court settles the issue
Read more
17/03/2026

Press releases

CBA advises Caronte & Tourist on new financing transaction
Read more
08-03-2026

Press reviews

Pink Power 2026 – Female leadership on the rise in Italian law firms
Read more
05-03-2026

Press reviews

Women in Legal Business
Read more
05-03-2026

Press reviews

The La Perla case and the outlook for cross-border insolvency proceedings
Read more
27-02-2026

Press reviews

Proving ownership of securitised receivables: new guidance from the Supreme Court
Read more
27-02-2026

Press reviews

Arera’s inspection powers: law, practice and European standards
Read more
22-02-2026

Press reviews

Italian patents on the decline: warning signs for innovation?
Read more
19-02-2026

Press releases

CBA advises Hi-Dec Edizioni on Alcedo SGR’s acquisition of a 70% stake in EDG
Read more
19-02-2026

Press reviews

Corporate governance reform: will it make the Italian market more attractive to foreign capital?
Read more
17-02-2026

Press reviews

Exceeding length limits in Supreme Court appeals: cost sanctions confirmed
Read more
12-02-2026

Press reviews

Rising material costs: how the new price adjustment mechanism in public procurement works
Read more
12-02-2026

Press releases

CBA advises BCC Garda, BCC Milano and BCC Agrobresciano on a €15 million financing for Fondazione Poliambulanza
Read more
05-02-2026

Press reviews

PDOs and PGIs: protection goes beyond the “name” itself
Read more
30-01-2026

Press reviews

Terzo Millennio: Automated decision-making and legal liability
Read more

THIS WEBSITE IS ECO-SUSTAINABLE AND REDUCES THE IMPACT OF CO2 IN THE ATMOSPHERE
Here’s an estimate of our emissions in real time

© 2026
ITA
magnifiercrosschevron-downchevron-leftchevron-right linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram